After Assembling your Irrigation Line (Part 6 of 7), your Flex Acre is built and ready for function testing. Follow these steps to run a leak check on your water lines, confirm your Light Bars come on, and place your decals.
Keep your water level between the MIN and MAX lines for the whole test, not only at first fill. Your Tank holds roughly 80 gallons in operation, so watch the Water Level Tool as the hose runs rather than checking it once at the end.
A fitting that is seated but not locked will hold at rest and let go under pump pressure, which is what the next step is looking for. Your 2 valves matter in opposite directions: a closed Main Send Valve starves your Drip Lines, and an open Drain Valve sends your tank water onto the floor.
CAUTION: Keep water away from your Light Bars while the pump runs. The Light Bars are not waterproof.
If you find water escaping, unplug the pump, reseat the leaking fitting, and plug the pump back in. Walk your Flex Acre again, and repeat until every fitting runs dry. A run time of 10 minutes with no leaking marks success.
If you skipped seating your Panel Plugs during assembly, use caution through this test as water can spray out of the open plant spaces and trip your lights.
If your lights do not come on, check both GFCI Adapters first and confirm neither one has tripped. If they are still dark, inspect the wiring and confirm every connection is solid. Your Light Bars run 18 continuous hours per day, 16 hours at minimum. That is the schedule your timers hold from here on, and it is on your Quick Reference Guide.
The front is typically the side facing the door to the room or another viewing space.
Commissioning is handled separately by Fork Farms, so your assembly is finished once your leak check and your lights pass. Everything after this point is the operating side of your Flex Acre.
Your Flex Acre is assembled, dry and lit. Well done!